Offshore Consent Application, Addendum – August 2018

Web EditorNews

In March 2018 NnGOWL submitted a new consent application to the Scottish Ministers, featuring an updated design for the wind farm. The updated design will allow the wind farm to be constructed using higher capacity turbines, meaning the same 450MW output could be achieved using fewer turbines.  The maximum number of turbines would therefore drop from 75 to 54.

An addendum to the application featuring some technical ornithology information was recently submitted to the Scottish Ministers and can be viewed on this website.  The ‘public notice’ includes information on how to respond to the addendum: https://nngoffshorewind.com/downloads/