Construction of NnG’s Operations and Maintenance base (O&M) in Eyemouth is really taking shape. This drone footage from Peter Devlin …
Abnormal Load Deliveries (December 2021)
Two very sizeable transformers that will help connect the NnG offshore wind farm to the National Grid will be delivered …
Abnormal Load Deliveries (November 2021)
The delivery of two transformers to the site of the NnG onshore substation is expected to take place in November. …
First of NnG’s offshore substation topsides loaded in Rotterdam
The first of NnG’s two offshore substation topsides was recently loaded onto the barge ’Louis’ by the GE-HSM consortium at …
NnG’s spare export cable delivered safely to the Port of Rosyth
A 100 ton spare export cable for the Neart na Gaoithe (NnG) Offshore Wind Farm has arrived at the Port …
NnG supply chain case study – Ashtead Technology
The Scottish supply chain is playing a significant role in the development of the NnG offshore windfarm, and we’ve been …
37km offshore cable will connect NnG to onshore substation
The first of two export cables, each 37 kilometres in length, has been installed at the nearshore of Thorntonloch Beach …
Offshore Cable Installation Campaign
Offshore construction of Neart na Gaoithe (NnG) offshore wind farm is well underway since it began in August 2020. Over …
Two Scottish based companies selected to build NnG’s O&M base
Neart na Gaoithe (NnG) Offshore Wind Limited has appointed two Scottish based businesses to construct its Operations and Maintenance (O&M) …